HWY 401 Overpass

Year: 2012
Client: MTO by way of Bray Construction
Cost: $185,000
HWY 401 Overpass

Engineering, management, planning, and execution of a mechanical demolition of a 85 meter long, 23 meter wide reinforced concrete bridge structure over both east and west bound highway lanes at Moulinette Rd., in Long Sault, ON.

The demolition entailed strategic traffic management and re-routing to facilitate an 8 hour full closure of traffic lanes for each direction. The structure was completely demolished and removed from the highway including the highway surface protection system with time to spare over the duration of the lane closures.